The Planned Outage Report provides the date and duration of planned TransGas work which will result in a partial or full interruption of receipt and delivery service to customers. This report is intended to provide an early notice to customers to help in the planning of their own facility maintenance work. This summary excludes planned outages that are scheduled during customer planned shutdowns. Where possible, TransGas will work with customers to minimize the outage impact, and schedule the planned TransGas work to coincide with customer maintenance or downtime. Please contact your Key Account Manager for further information.

Click for map view

REMAINING 2017 OUTAGES IMPACTING CUSTOMERS
Published Date: 28 April 2017 02:21 pm

#

PROJECT
DURATION
(Days)
START
DATE
CAPACITY
AVAILABLE
RECEIPT CUSTOMERS
AFFECTED
DELIVERY CUSTOMERS
AFFECTED
1 Intergity Tool Runs 2 May 2 100% (Pressure Only)   Meter #1686
2 Facility Improvements 5 June 2 0%   Meter #9842
3 Reduced Pressure Operation 5 June 0%   Meter #7000
4 System Integrity Modifications 2 June 0%   Meter #7710
5 Facility Improvements 1 June 0% Meter #2501, #2502, #2703  
6 Facility Improvements 1 July 5 70% Meter #1608, #1726, #6258, #6337, #7084, #8656, #8036, #8740, #8762  
7 System Integrity Modifications 4 July 12 0%   Meter #6702, #7102, #7720
8 Facility Improvements 5 July 0%   Merter #7735
9 System Integrity Modifications 1 July TBD   Meter #1690
10 Facility Integrity Inspections 7 July 0%   Meter #7718
11 System Integrity Modifications 1 July 0%   Meter #7775
12 System Integrity Modifications 2 August 0%   Meter #7710
13 System Integrity Modifications 1 August TBD   Meter #8770
14 System Integrity Modifications 1 September 0% Meter #7056  
15 Integrity Tool Runs 3 September 30% Meter #1608, #1726  
16 System Integrity Modifications 1 September 0% Meter #2508, #2538, #2545, #6273  
17 Facility Improvements 4 September 0%   Meter #7736, #7780
18 Reduced Pressure Operation 5 September 0% Meter #4507  
19 System Integrity Modifications 1 October 0% Meter #2508  
20 System Integrity Modifications 1 October 0% Meter #2514  
21 Facility Improvements 1 2017 0% Meter #3015  
22 Facility Improvements 1 2017 0% Meter #6274  
23 Facility Improvements 1 2017 0% Meter #4654  
24 Facility Improvements 1 2017 0% Meter #4772  
25 Facility Improvements 1 2017 0% Meter #6253  