Planned Outages

The Planned Outage Report provides the date and duration of planned TransGas work which will result in a partial or full interruption of receipt and delivery service to customers. This report is intended to provide an early notice to customers to help in the planning of their own facility maintenance work. This summary excludes planned outages that are scheduled during customer planned shutdowns. Where possible, TransGas will work with customers to minimize the outage impact, and schedule the planned TransGas work to coincide with customer maintenance or downtime. Please contact your Key Account Manager for further information.

Click for map view

REMAINING 2019 OUTAGES IMPACTING CUSTOMERS
Published Date: 11 June 2019 11:24 am

#

PROJECT
DURATION
(Days)
START
DATE
CAPACITY
AVAILABLE
RECEIPT CUSTOMERS
AFFECTED
DELIVERY CUSTOMERS
AFFECTED
1 New Customer Tie-in 1 July 10   Meter #1608, #6258, #7084, #6337, #8036, #8740, #8656, #1726, #8762  
2 System Improvements 1 July 12   Meter #2536  
3 System Integrity Modifications 1 July 17   Meter #1608, #6258, #7084, #6337, #8036, #8740, #8656, #1726, #8762  
4 System Improvements 1 July 18   Meter #2525  
5 System Integrity Inspections 2 July 22     Meter #7773
6 System Improvements 1 Q3   Meter #4775  
7 System Integrity Modifications 2 Q3   Meter #4654 Meter #1687, #4747
8 System Integrity Modifications 1 Q3   Meter #6291  
9 System Improvements 1 Q3   Meter #1666  
10 System Integrity Digs 2 Q3   Meter #4656  
11 System Integrity Modifications 2 Q3     Meter #4709
12 System Improvements 1 Q3   Meter #6262  
13 System Integrity Modifications 1 Q3     Meter #6484, #9241, #9831 (potential)
14 System Integrity Modifications 2 Q3   Meter #4668 Meter #4662, #4667
15 System Integrity Modifications 2 Q3     Meter #5704 (potential)
16 System Integrity Tool Runs 1 Q3   Meter #2512  
17 System Integrity Modifications 3 Q3   Meter #8638, #1744, #6274  
18 System Integrity Mods 2 Q3     Meter #8738, #8627
19 System Integrity Inspections 1 Q3   Meter #2514  
20 System Integrity Digs 2 Q3   Meter #2501, #2502, #2703  
21 System Integrity Digs 2 Q3     Meter #1683 (potential)
22 New Customer Tie-in 1 Q3   Meter #5066 Meter #8631, #1733, #7760
23 System Integrity Inspections 1 Q4     Meter #8656
24 System Integrity Tool Runs 2 Q4   Meter #2523  